| Saturday 21st July  Today work continued on the cooler group rebuild, the Gloucester lads were in 
  attendance for the day and their first task was to adjust the left hand 
  cooler group tank so that radiator elements fitted properly to both top and 
  bottom rails. With this done, they then set about fitting one of the bottom 
  tank coolant pipes and the bottom oil tank balance pipe. One of the lads 
  continued the undercoating of No1 end nose compartment in readiness for 
  gloss being applied. More cooler group water pipework was cleaned up and 
  given a coat of primer. The opportunity was also taken this day to remove 
  the covers between the power unit and main generator, this is so we could 
  ascertain how the pair fit together in readiness for splitting them off 
  later this year. 
 Sunday 22nd July  Only a handful of members present today. More cooler group components were 
  cleaned up and given the paint treatment today, these mainly being the fan 
  drive shafts and the water pipes were given a coat of undercoat. With the 
  undercoat now dry in No1 end nose compartment, the roof and walls were given 
  a coat of grey gloss, it just needs the floor catching up now for this compartment to be ready for parts to be fitted back in.
 
 Monday 23rd  July  Three of us were away from work for the next few days, so the opportunity 
  for a mid week work session was taken. Today we managed to test the oil 
  thermostat valve (or Ted valve as its now become! short for Teddington valve 
  who manufactured it) This involved stripping the Ted down, the wax element 
  was then placed in a pan (sorry Linda!) of hot water and heated up even more, 
  this was to check the temperature it started to open and was fully open 
  using a thermometer. It was then rebuilt and tested again, to ensure that 
  the valve was moving ok and nothing stuck either shut or open. Once done, we 
  headed off down to the coach to apply gloss to the water pipes and prep and 
  prime the Ted valve.
 
 Tuesday 24th  July  Three of us present again, we headed off down the coach and first job was to 
  apply gloss to the Ted valve and fan drive shafts. We then set about fitting 
  two pieces of conduit on the left hand side floor of the cooler group that 
  had been missed previously, but in order to do this properly two long runs of 
  conduit needed removing from the engine compartment, so out came the 
  wire brushes, WD40 and brute force! Gaskets were made for the top water pipes 
  and oil pipes ready for refitting.
 A mega was borrowed from Castlecroft so 
    we could get a general idea what condition the electrical left on D8233 were 
    in after 20 years being stood. The results were surprising, the main 
    generator and aux generator showed a good reading considering the amount of 
    time they have been stood idle, the exciter's reading was even better, and 
    the compressor motor's reading was as if it was brand new! The two 
    exhausters reading were very low compared to the rest, but as all the motors 
    on D8233 will be looked at and given a overhaul before use they shouldn't 
    pose a problem. 
    The top water pipes, were then refitted along with some of the top oil pipes 
    in the cooler group then we all called it a day! 
 Wednesday 25th of July
 Three became one today, as two of us had to return to the daily grind of home life 
    and work! However Jason Lovell forged ahead with cooler group rebuild a 
    short note of what he did is below:
 
 Had a bit of a general tidy up in the support coach.
 Then spent the rest of the day sorting out the sales stand stock and reboxing everything.
 
 Thursday 26th July 2007 I made some additional gaskets for the Ted Valve and then fitted the valve to the base mounting pipe. Took the Ted valve assembly into the cooler group and fitted to the base plate on the floor & pipe flange to the bulkhead. 
    I fitted the two outlet pipes to the valve, sealing the joints with the red gastight sealant.  
    The Ermeto joints were then loosened to help locate the oil pipe flanges on the top radiator tanks. Once located, sealed & bolted down tight the L/H top oil pipe flange mounting. The R/H top oil pipe flange and then tightened all Ermeto joints as much as possible.
 
 Friday 27th July 2007 Drelled radiator shutter air pipes they came out bright copper/brass finish, decided to fit unpainted. In the cooler group the shutter air pipes, bulkhead clamps were fitted and all joints tightened. Various cooler group components were located and prepared for fitting in the next working weekend. These included the large pipe clamp that fits the top of the oil bypass pipe, the fan drive couplings, filter drip tray drain pipe, fan brace bars and hanging brackets.
   Over the seven days a lot was achieved, the cooler group is very nearly 
  finished, the radiator fan itself is now away for repair and should be back 
  at Bury in the not to distant future, everything left to rebuild in the compartment is fan related (bar the elements) we are hoping that by September 
  the cooler group will be done and we can move onto the engine compartment 
  and No1 compartment.
 Some photos of the work are below.  |