Progress reports:
We intend to keep this section as up-to-date as possible! Click the dates to find out what we have been up to.
| Date | Summary |
| 11 December 2011 | Restoration of D8233 continues. |
| 29-30 October 2011 | Restoration of D8233 continues. |
| 10-11 September 2001 | Restoration of D8233 continues. |
| 09 September 2011 | A set of bogies are acquired. |
| 06-07 August 2011 | Restoration of D8233 continues. |
| 30 July 2011 | Restoration of D8233 continues. |
| 23-24 July 2011 | Restoration of D8233 continues. |
| 09-10 July 2011 | Restoration of D8233 continues. |
| 04-07 July 2011 | July Working Week |
| 02 July 2011 | D8233 moves under cover. |
| 25-26 June 2011 | Restoration of D8233 continues. |
| 11 June 2011 | Restoration of D8233 continues. |
| 18-19 December 2010 | Restoration of D8233 continues. |
| 13-14 November 2010 | Lifting Weekend |
| 06-07 November 2010 | AGM Weekend |
| 23-24 October 2010 | Restoration of D8233 continues. |
| October 2010 | Two exhausters overhauled |
| 25-26 September 2010 | Restoration of D8233 continues. |
| 31 July & 1 August | Restoration of D8233 continues. |
| 18-20 June 2010 | Engine Start Up ! |
| 05-06 June 2010 | Preparation for engine start |
| 22-23 May 2010 | Preparation for engine start |
| 08-09 May 2010 | Preparation for engine start |
| 20-24 April 2010 | Rebuilding the engine exhaust system. |
| 19 April 2010 | Installation of overhauled generators. |
| 17-18 April 2010 | Preparation to install overhauled generators. |
| 23-24 March 2010 | Cab and nose end return from the shotblasters. |
| 13-15 March 2010 | Cab Removal. |
| 13-14 February 2010 | Preparations to remove the cab. |
| 30-31 January 2010 | Restoration of D8233 continues. |
| 12-13 December 2009 | Restoration of D8233 continues. |
| 14-15 November 2009 | AGM Weekend. |
| 10-11 October 2009 | Preparation to remove the Cab. |
| 12-13 September 2009 | Restoration of D8233 continues. |
| 15-16 August 2009 | Restoration of D8233 continues. |
| 01-02 August 2009 | Restoration of D8233 continues. |
| 17-18 July 2009 | Restoration of D8233 continues. |
| 20-21 June 2009 | Restoration of D8233 continues. |
| June 2009 | Rebuilding of Traction Motor Blower #1. |
| 23-24 May 2009 | Restoration of D8233 continues. |
| 9 May 2009 | Restoring the bodyside doors. |
| 25-26 April 2009 | Restoration of D8233 continues. |
| 11-12 April 2009 | Restoration of D8233 continues. |
| 28-30 March 2009 | Restoration of D8233 continues. |
| 14-15 March 2009 | Restoration of the cab starts. |
| 28 February - 1 March 2009 | Restoration of D8233 continues. |
| 14 February 2009 | Restoration of D8233 continues. |
| 31 January-1 February 2009 | Restoration of D8233 continues. |
| 13-14 December 2008 | Restoration of D8233 continues. |
| 28th November-1st December 2008 | Refitting bodyside doors & AGM. |
| 08-09 November 2008 | Restoration of D8233 continues. |
| 25-26 October 2008 | Restoration of D8233 continues. |
| 15 October 2008 | Generator taken for overhaul. |
| 04-05 October 2008 | Restoration of D8233 continues. |
| 19-21 September 2008 | Restoration of D8233 continues. |
| 06-07 September 2008 | Restoration of D8233 continues. |
| 23 August 2008 | Restoration of D8233 continues. |
| 09-10 August 2008 | Restoration of D8233 continues. |
| 19-20 July 2008 | Restoration of D8233 continues. |
| 02 July 2008 | Shunt D8233 back into position at Baron Street. |
| 08-10 May 2008 | Attempted engine start up. |
| 12-13 April 2008 | Complete cooler group and prepare engine for start up. |
| 28-29 March 2008 | Complete water and oil system. Prepare engine for start up. |
| 28 February 2008 | Fitting the fan drive shaft. |
| 22 February 2008 | Work concentrating on the cooler group. |
| 09-10 February 2008 | Work on the getting the engine ready for start up continues. |
| 04-05 February 2008 | Work concentrating on the cooler group. |
| 26-27 January 2008 | Work on the getting the engine ready for start up continues. |
| 12-13 January 2008 | Work on the engine and associated pipework. |
| 17-18 November 2007 | Re-assembly of the cooler group continues. |
| 20-21 October 2007 | The new power unit is craned into D8233 |
| 15-19 October 2007 | Cleaning and painting engine bay. |
| 12-14 October 2007 | The old power unit is lifted out. |
| 23-24 September 2007 | Restoration of D8233 & preparing for power unit lift. |
| 08-09 September 2007 | Preparing D8233 for power unit lift. |
| 28 August 2007 | Fan & Fan Drive returned after overhaul. |
| 04-05 August 2007 | Re-assembly of the cooler group continues. |
| 21-27 July 2007 | Working Week. |
| 16 & 17 June 2007 | Re-assembly of the cooler group continues. |
| 02 & 03 June 2007 | Re-assembly of the cooler group continues. |
| 26 & 27 May 2007 | Re-assembly of the cooler group begins. |
| 15 & 16 May 2007 | Restoration of D8233 continues. |
| 28 & 29 April 2007 | Restoration of D8233 continues. |
| 21 April 2007 | Replacement traction motor bearings arrive at Bury. |
| 01-02 April 2007 | Restoration of D8233 continues. |
| 31 March 2007 | Oil priming pump overhaul completed. |
| 17 & 18 March 2007 | Restoration of D8233 continues. |
| 24 & 25 February 2007 | A new tarpaulin to protect D8233. |
| 03rd & 04th February 2007 | Restoration of D8233 continues. |
| 14 January 2007 | Restoration of D8233 continues. |
| 09 & 10 December 2006 | Restoration of D8233 continues. |
| 11 & 12 November 2006 | Restoration of D8233 continues. |
| 10 November 2006 | Replacement electrical components sourced. |
| 14th & 15th October 2006 | Stripping down D8233. |
| 23rd & 24th September 2006 | Stripping down D8233. |
| 19th & 20th August 2006 | Stripping down D8233. |
| 05th & 06th August 2006 | Stripping down D8233. |
| 02 August 2006 | Overhauled fan drive gearbox is delivered. |
| 01 August 2006 | A new power unit is secured. |
| 22nd & 23rd July 2006 | Stripping down D8233. |
| 10th & 11th June 2006 | Stripping down D8233. |
| 02 June 2006 | Replacement power controllers sourced. |
| 27th & 28th May 2006 | Stripping down D8233. |
| 13th & 14th May 2006 | Stripping down D8233. |
| 22nd & 23rd April 2006 | Stripping down D8233. |
| 08th & 09th April 2006 | Stripping down D8233. |
| 18th & 19th March 2006 | Stripping down D8233 begins. |
| 10th February 2006 | D8233 on the move. |
| 14th January 2006 | Preparing to move D8233 to its new location. |